Location
360 Elizabeth StreetArea
450sqmValue
$1.1mDuration
16 weeksEngagement
Fixed Lump SumCollaborators
Accuraco, Gray Puksand, TJ ConsultingThis project was part of a larger base building upgrade programme of works and GPT’s key objective was time, cost and quality along with delivering with minimal disruption.
Working under challenging live environment conditions with the tenant in occupation, the project was delivered via a multi staged approach with works carefully sequenced with noisy and intrusive works scheduled out of hours to minimise disruption. A safe path of travel from the lifts to the tenancy was always maintained.