• Location

    Levels 7-8, 79-89 Wellington Street
  • Area

    1,500sqm
  • Value

    $2.4M
  • Duration

    14 weeks
  • Engagement

    Early Contractor Involvement
  • Collaborators

    Neoscape, Mooki

Overview
  • High-end finishes
  • Internal stair
  • Occupied building
  • Value management


When Quest/The Ascott Limited was looking to move its headquarters into levels 7 & 8 of its Wellington Street property, Capabuild was only too happy to assist — and give a warm welcome to our new Collingwood neighbours.

With both levels cold shell, we took on an ECI role to help finalise the design in line with the client’s budget, value managing the project extensively to achieve cost goals.

A major consideration during works was minimising disruption to hotel guests, as the property remained fully operational during the build. To accommodate this, our team adjusted the schedule for noisy works, allowing the hotel to run at capacity and hold several major events without disturbance or delay.

Installing the 2-level stair presented challenges, working in a live environment and navigating the foyer and small lift with building materials.

We overcame these issues by undertaking a thorough investigation of site ahead of the stair works and amending our plans to work in line with the size limitations of the space.

When it was discovered that the building had been handed over to the client with deficiencies in the ceiling’s insulation requirements, we were able to create a design that allowed the insulation to be installed without having to remove the wholesale mechanical units in the roof.

Quest/The Ascott was thrilled with the end results, bringing its team to occupy this fantastic new head office space — and thanks to a great working relationship, they’ve since enlisted Capabuild to take on additional Quest projects.

01
 — 05

Similar Projects

View all project