Location
Burwood CampusArea
400sqmValue
$1.5mDuration
12 weeksEngagement
Fixed Lump SumCollaborators
Deakin University, DS Architects, EngineerThe high-end design of the teaching spaces, complemented by a state-of-the-art audio visual package, incorporates concealed structure to support the equipment, material selection to improve acoustics, high-end wall panelling and bespoke joinery.
Key to the success of this project was the detailed design workshopping process during the pre-construction phase, ensuring the design and the client and designers’ expectations were aligned. Shop drawings and control sample sign-offs were effectively implemented to manage quality.
Delivered in an occupied building under live environment conditions, the project presented several logistical challenges resulting in some out-of-hours deliveries and works. The results speak for themselves and pleasingly this project strengthened our existing relationship with Deakin leading to future opportunities.